Question
1 Approved Answer
If the EVM estimated price at completion is higher than the program budget the business/financial manager should: (select 2 answers): 1. determine the amount of
If the EVM estimated price at completion is higher than the program budget the business/financial manager should: (select 2 answers):
1. determine the amount of the spending shortfall
2. decide when additional will be required for the contract
3. decide when excess funds can be used for another program effort
4. determine the amount of the funding excess
BUS 1100 (Mod 3-6)
Step by Step Solution