Question

1 Approved Answer

If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60

image text in transcribed

If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23 days, and $50 for 22 days, compute the direct, indirect, and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $10 for every day you shorten the project from your original network. Would you take it? If so, for how many days?

Use the table and image below to assist you in this learning activity:

image text in transcribedimage text in transcribed
L+ Time and Costs Act. Crash Cost (slope) Maximum Crash Time Normal Time Normal Cost A 80 2 10 40 B 30 3 8 10 C 40 5 80 D 50 N 11 50 E 100 4 15 100 F 30 6 20 Total: 300A D Project duration = 27 10 11 B F 8 6 C E 5 15 Total direct cost = $300.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

MIS Essentials

Authors: David M Kroenke

1st Edition

0136075606, 9780136075608

More Books

Students also viewed these General Management questions

Question

A greater tendency to create winwin situations.

Answered: 1 week ago

Question

Improving creative problem-solving ability.

Answered: 1 week ago