If the production schedule calls for assembly of 500 motorcycles, then the 1,000 wheels and 1,000 tires that are required to produce the 500 motorcycles
If the production schedule calls for assembly of 500 motorcycles, then the 1,000 wheels and 1,000 tires that are required to produce the 500 motorcycles are classified as ______. Group of answer choices dependent demand items independent demand items inelastic demand items inelastic supply items