If the project has a TVAC=-11, which of the following is a corrective action that you can not put in action? a. add 2 resources
- If the project has a TVAC=-11, which of the following is a corrective action that you can not put in action?
a. add 2 resources to a non critical WP
B. find a cheaper labour supplier
C. ask a discount for an expensive furniture
D. outsource a critical WP in order to modify its logical link from FS to SS