If the project is to be completed by June 30, the production must begin on June 15, the raw materials must be in house by
If the project is to be completed by June 30, the production must begin on June 15, the raw materials must be in house by June 1, and the contract has to be signed by May 15. These are examples of: operational controls. strategic controls. structural controls performance indicators. qualty assurance