If the SPI of a project is 0.6, which of the following is most likely to be a true statement, assuming that no corrective actions
If the SPI of a project is 0.6, which of the following is most likely to be a true statement, assuming that no corrective actions are initiated in the future?
a. The project is likely to finish on schedule
b. The project is likely to slip the schedule
c. The project has exactly a 60% chance of slipping the schedule
d. The project is likely to finish ahead of schedule