If the standard quantity of materials is 84,300 units at $0.15 per unit and the actual quantity is 94,800 units at $0.12 per unit, then
If the standard quantity of materials is 84,300 units at $0.15 per unit and the actual quantity is 94,800 units at $0.12 per unit, then the total materials cost variance is:
- $2,844 Favorable.
- $1,575 Unfavorable.
- $2,844 Unfavorable.
- $1,269 Favorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1