If the standard quantity of materials is 84,600 units at $0.16 per unit and the actual quantity is 95,100 units at $0.13 per unit, then
If the standard quantity of materials is 84,600 units at $0.16 per unit and the actual quantity is 95,100 units at $0.13 per unit, then the materials quantity variance is: Multiple Choice $1,173 Favorable. O O $2,853 Unfavorable. $2,853 Favorable. O O $1,680 Unfavorable