If the standard quantity of materials is 85,000 units at $0.14 per unit and the actual quantity is 95,500 units at $0.11 per unit, then
If the standard quantity of materials is 85,000 units at $0.14 per unit and the actual quantity is 95,500 units at $0.11 per unit, then the materials price variance is:
Multiple Choice
- $1,470 Unfavorable.
- $2,865 Unfavorable.
- $1,395 Favorable.
- $2,865 Favorable.