Question
1 Approved Answer
If two activities have the same predecessor activity, when calculating the Latest Finish time for the predeceasing activity you must choose which Latest start time?
If two activities have the same predecessor activity, when calculating the Latest Finish time for the predeceasing activity you must choose which Latest start time? The largest latest start time The one with the largest slack time The one with the earliest latest start time The one with the longest duration