Question

1 Approved Answer

If two activities have the same predecessor activity, when calculating the Latest Finish time for the predeceasing activity you must choose which Latest start time?

If two activities have the same predecessor activity, when calculating the Latest Finish time for the predeceasing activity you must choose which Latest start time? The largest latest start time The one with the largest slack time The one with the earliest latest start time The one with the longest duration

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Risk Management

Authors: Paul Hopkin

5th Edition

0749483075, 978-0749483074

More Books

Students also viewed these General Management questions

Question

Have you laid out a timeframe for refreshing the data regularly?

Answered: 1 week ago

Question

Have you laid out the information as clearly as possible?

Answered: 1 week ago

Question

Have you tested your findings with those closest to the market?

Answered: 1 week ago