Question

1 Approved Answer

If you are using the PERT 3-point estimating method and you have a Pessimistic duration (P) of 20 days, an Optimistic duration (O) of 11

If you are using the PERT 3-point estimating method and you have a Pessimistic duration (P) of 20 days, an Optimistic duration (O) of 11 days, and a most likely duration (M) of 14 days, then what is the expected duration (E)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Motivated

Authors: For Goodness Sake Network

1st Edition

B0CNMLYFJ3

More Books

Students also viewed these General Management questions

Question

relate the value and types of incentives

Answered: 1 week ago