Answered step by step
Verified Expert Solution
Question
1 Approved Answer
If you are using the PERT 3-point estimating method and you have a Pessimistic duration (P) of 20 days, an Optimistic duration (O) of 11
If you are using the PERT 3-point estimating method and you have a Pessimistic duration (P) of 20 days, an Optimistic duration (O) of 11 days, and a most likely duration (M) of 14 days, then what is the expected duration (E)?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started