Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

If your client asks you to stop all work on the project today, EV tells you the value the project has generated, considering work done

If your client asks you to stop all work on the project today, EV tells you the
value the project has generated, considering work done to date.
Earned value formula
To get the earned value, multiply the percentage of completed work (actual)
by the project's budget (BAC).
EV=% complete (actual)x BAC
Let's look at some examples:
You spent $750 after the first month and you only completed 20% of
the project.
Given:
Project duration: 4 months
Project budget (BAC): $4,000
Elapsed time: 1 month
Planned value: $1,000
Actual cost: $750
% complete (planned): 25%
% complete (actual): 20%
EV=% complete (actual) xBAC
WHAT IS THE EV =
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing A Practical Approach with Data Analytics

Authors: Raymond N. Johnson, Laura Davis Wiley, Robyn Moroney, Fiona Campbell, Jane Hamilton

1st edition

1119401747, 978-1119401742

More Books

Students also viewed these General Management questions

Question

What is cultural awareness?

Answered: 1 week ago

Question

8.2 Explain the purpose of onboarding programs.

Answered: 1 week ago