III. Interest Cost Capitalization On January 2, 2017, Indian River Groves began construction of a new citrus processing plant. The automated plant was finished and
III. Interest Cost Capitalization
On January 2, 2017, Indian River Groves began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2018. Expenditures for the construction were as follows:
January 2, 2017 $ 600,000
September 1, 2017 1,800,000
December 31, 2017 1,800,000
March 31, 2018 1,800,000
September 30, 2018 1,200,000
Indian River Groves borrowed $3,300,000 on a construction loan at 12% interest on January 2, 2017. This loan was outstanding during the construction period. The company also had $12,000,000 in 9% bonds outstanding in 2017 and 2018.
Instructions: Calculate the interest capitalized for 2017.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started