ILLUSTRATION 4: The standard and actual figures of a firm are as under Standard time for the job 1,000 hours Standard rate per hour &.

ILLUSTRATION 4: The standard and actual figures of a firm are as under Standard time for the job 1,000 hours Standard rate per hour &. 50 Actual time taken 900 hours Actual wages paid $ 36,000 CALCULATE variances.