iment 11: Chapter 11 EOC problems A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 + Project M -$12,000 $4,000 $4,000 $4,000 $4,000 $4,000 Project N -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 a. Calculate NPV for each project. Do not round Intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M: % Project N: % Calculate MIRR for each project. Do not round Intermediate calculations. Round your answers to two decimal places Project M: % Project N % Calculate payback for each project. Do not round Intermediate calculations. Round your answers to two decimal places Project M: years Project N: years Calculate discounted payback for each project. Do not round Intermediate calculations. Round your answers to two decimal places. Project M: years Project N: years Assignment 11: Chapter 11 EOC problems Calculate MIRR for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M: % Project N: % Calculate payback for each project. Do not round intermediate calculations. Round your answers to two decimal places. Project M years Project N: years Calculate discounted payback for each project. Do not round Intermediate calculations. Round your answers to two decimal places. Project M: years Project N: years b. Assuming the projects are independent, which one(s) would you recommend? -Select- c. If the projects are mutually exclusive, which would you recommend? -Select d. Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRR? -Select