In 2 0 2 2 , Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project

In 2022, Leo construction will work on a residential project that lasts 4 months. The direct costs of the residential project are shown in the following bar chart.
Question 1
5 pts
Assuming $5,000 indirect cost per month, and 10.1% markup. If the retainage is 7% throughout the project, finance charge is 1% per month, and payments will be billed at the end of the month and will be received one month later. How much is the last payment the contractor is expected to receive?ANSWER SHOULD BE LESS THAN 100,000
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Tools for Business Decision Making

Authors: Paul D. Kimmel, Jerry J. Weygandt, Donald E. Kieso, Barbara Trenholm, Wayne Irvine

6th Canadian edition

1118644948, 978-1118805084, 1118805089, 978-1118644942

Students also viewed these Finance questions