In 2 0 2 4 , the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $ 1

In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
202420252026
Cost incurred during the year $ 2,511,000 $ 3,645,000 $ 2,138,400
Estimated costs to complete as of year-end 5,589,0001,944,0000
Billings during the year 2,100,0004,056,0003,844,000
Cash collections during the year 1,900,0003,700,0004,400,000
Assume that Westgate Constructions contract with Santa Clara County does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2024(credit Cash, Materials, etc. for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2025(credit Cash, Materials, etc. for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2026(credit Cash, Materials, etc. for construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.
202420252026
Cost incurred during the year $ 2,410,000 $ 3,805,000 $ 3,210,000
Estimated costs to complete as of year-end 5,610,0003,110,0000
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.
202420252026
Cost incurred during the year $ 2,410,000 $ 3,805,000 $ 3,915,000
Estimated costs to complete as of year-end 5,610,0004,110,0000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Accounting With QuickBooks Online

Authors: Donna Kay

3rd Edition

1264127278, 9781264127276

More Books

Students also viewed these Accounting questions

Question

Design a cross-cultural preparation program. page 313

Answered: 1 week ago

Question

Evaluate employees readiness for training. page 289

Answered: 1 week ago