Question

1 Approved Answer

In 2 0 2 4 , the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $ 1

In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:On February 1,2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of
$8,330,000. During 2024, costs of $2,110,000 were incurred with estimated costs of $4,110,000 yet to be incurred. Billings of
$2,610,000 were sent, and cash collected was $2,360,000.
In 2025, costs incurred were $2,610,000 with remaining costs estimated to be $3,765,000.2025 billings were $2,860,000, and
$2,585,000 cash was collected. The project was completed in 2026 after additional costs of $3,910,000 were incurred. The
company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
Required:
Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31,2024.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31,2025.
Complete this question by entering your answers in the tabs below.
Req 1
Req 3A
Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Round your final answers to the nearest
whole dollar.
202420252026
Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400
Estimated costs to complete as of year-end 5,796,0001,764,0000
Billings during the year 2,040,0004,596,0003,364,000
Cash collections during the year 1,820,0004,000,0004,180,000
Westgate recognizes revenue over time according to percentage of completion.
3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting An Introduction

Authors: Jacqui Kew, Alex Watson

4th Edition

0199046484, 978-0199046485

More Books

Students also viewed these Accounting questions