In 2 0 2 5 , costs incurred were $ 2 , 6 8 0 , 0 0 0 with remaining costs estimated to be

In 2025, costs incurred were $2,680,000 with remaining costs estimated to be $3,870,000.2025 billings were $2,930,000, and
$2,655,000 cash was collected. The project was completed in 2026 after additional costs of $3,980,000 were incurred. The
company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
Required:
Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31,2024.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31,2025.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_step_2

Step: 3

blur-text-image_step3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

How would you rate your leaders against these criteria?

Answered: 1 week ago