In 2006/2007, the government of Ghana in response to the energy crisis commissioned the construction of a power dam at Bui in the Western region
- In 2006/2007, the government of Ghana in response to the energy crisis commissioned the construction of a power dam at Bui in the Western region to complement power supply in the country. The table below shows the flow of real benefits (i.e. direct and indirect) and real cost (i.e. direct and indirect) associated with the project for the next ten (10) years.
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
benefit |
| 300 | 450 | 580 | 630 | 1000 | 1200 | 2000 | 2100 | 4000 |
Cost | 3000 | 2500 | 1800 | 1000 | 500 | 350 | 300 | 280 | 230 | 150 |
- Using a discount rate of 5 percent, compute the net present value of the project.
- Comment on the viability of the project
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started