In 2011, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC uses the percentage-of-completion method to account for such projects

In 2011, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC

uses the percentage-of-completion method to account for such projects and provides you with the following

information (dollars in millions):

What are CCC's estimated remaining construction costs on the project at the end of 2011?

Accounts receivable (from construction progress billings) $37.5

Actual construction costs incurred in 2011 $135

Cash collected on project during 2011 $105

Construction in progress, 12/31/11 $207

Estimated percentage of completion during 2011 60%

A. $0

B. $225 million

C. $90 million

D. $135 million

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started