Question

1 Approved Answer

In 2013, Fargo Corporation began construction work under a three-year contract. The contract price is $3,600,000. Fargo uses the percentage-of-completion method for financial accounting purposes.

In 2013, Fargo Corporation began construction work under a three-year contract. The contract price is $3,600,000. Fargo uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2013, follow:

Balance Sheet

Accounts receivableconstruction contract billings $150,000

Construction in progress $450,000

Less contract billings 360,000

Costs and recognized profit in excess of billings 90,000

Income Statement

Income (before tax) on the contract recognized in 2013 $90,000

What was the initial estimated total income before tax on this contract?

a. $450,000

b. $480,000

c. $600,000

d. $720,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ethical Obligations and Decision Making in Accounting Text and Cases

Authors: Steven M. Mintz, Roselyn E. Morris

5th edition

1259969460, 73403997, 1260480852, 978-1259969461

More Books

Students also viewed these Accounting questions

Question

An action plan is prepared.

Answered: 1 week ago