In 2013, the Westgate Construction Company entered a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2015.
In 2013, the Westgate Construction Company entered a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2015. Information related to the contract is as follows: |
| 2013 | 2014 | 2015 | ||||||
Cost incurred during the year | $ | 2,511,000 |
| $ | 3,645,000 |
| $ | 2,138,400 |
|
Estimated costs to complete as of year-end |
| 5,589,000 |
|
| 1,944,000 |
|
| 0 |
|
Billings during the year |
| 2,100,000 |
|
| 4,056,000 |
|
| 3,844,000 |
|
Cash collections during the year |
| 1,890,000 |
|
| 3,700,000 |
|
| 4,410,000 |
|
Westgate uses the percentage-of-completion method of accounting for long-term construction contracts. |
Required: |
1. | Calculate the amount of gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations.) |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started