In 2016, Johnson Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the

In 2016, Johnson Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows: Costs incurred during the year Estimated costs to complete Partial billings Collections B) $659,600 OC) $680,000 2016 $238,000 357,000 260,000 240,000 Assuming the performance obligation is satisfied over time, what would be the balance in Construction in Progress at the end of 2017? OA) $557,600 D) $782,000 2017 $319,600 139,400 210,000 200,000 2018 $105,000 -0- 380,000 410,000
image text in transcribed
In 2016, Johnson Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows: Assuming the performance obligation is satisfied over time, what would be the balance in Construction in Progress at the end of 2017 ? A) $557,600 B) $659,600 C) $680,000 D) $782,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Financial Accounting

Authors: John J. Wild, Ken W. Shaw, Barbara Chiappetta

21st Edition

0077525264, 978-0077525262

More Books

Students also viewed these Accounting questions