Question
In 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,100,000. Long recognizes revenue over time according to percentage
In 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,100,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2016, is as follows:
Accounts receivable (from construction progress billings): $35,000
Construction in progess: $150,000
Less: Billings on construction contract: (143,000)
Cost and profit of uncompleted contracts in excess of billings: 7,000
Income (before tax) on the contract recognized in 2016: $25,000
Required:
1. What was the cost of construction actually incurred in 2016? $125,000
2. How much cash was collected in 2016 on this contract? $108,000
I know question one and two is correct. I'm having trouble figuring out questions three and four
3. What was the estimated cost to complete as of the end of 2016?
4. What was the estimated percentage of completion used to calculate revenue in 2016? (Do not round intermediate calculations. Round your percentage answer to 2 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started