In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows:
| 2016 | 2017 | 2018 |
Cost incurred during the year | $2,072,000 | $2,738,000 | $2,849,000 |
Estimated costs to complete as of year-end | $5,328,000 | $2,590,000 | 0 |
Billings during the year | $2,160,000 | $2,650,000 | $5,190,000 |
Cash collections during the year | $1,880,000 | $2,700,000 | $5,420,000 |
Westgate recognizes revenue over time according to percentage of completion.
Required:
Calculate the amount of revenue and gross profit to be recognized in each of the three years.
| 2016 | 2017 | 2018 |
Revenue |
|
|
|
Gross profit (loss) |
|
|
|
In the journal below, complete the necessary journal entries for the year 2016 (credit Various Accounts for construction costs incurred). (If no entry is required for a transaction/event, No journal entry required).
Record construction costs
Record progress billings
Record Cash Collections
Record Gross Profit
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started