In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows: |
2016 | 2017 | 2018 | |||||||
Cost incurred during the year | $ | 2,610,000 | $ | 3,162,000 | $ | 2,230,800 | |||
Estimated costs to complete as of year-end | 6,390,000 | 2,028,000 | 0 | ||||||
Billings during the year | 2,100,000 | 3,672,000 | 4,228,000 | ||||||
Cash collections during the year | 1,850,000 | 3,000,000 | 5,150,000 | ||||||
Complete the information required below to prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or contract liabilities. (Do not round intermediate calculations.)
** just need help finding theaccounts receivable for the balance sheet.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started