Question
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows: |
2016 | 2017 | 2018 | |||||||
Cost incurred during the year | $ | 2,184,000 | $ | 3,510,000 | $ | 2,316,600 | |||
Estimated costs to complete as of year-end | 5,616,000 | 2,106,000 | 0 | ||||||
Billings during the year | 2,120,000 | 3,574,000 | 4,306,000 | ||||||
Cash collections during the year | 1,860,000 | 3,400,000 | 4,740,000 | ||||||
|
Westgate recognizes revenue over time according to percentage of completion. |
Required: |
1. | Calculate the amount of revenue and gross profit to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started