Question
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows |
2016 | 2017 | 2018 | |
cost inccured during the year | 2,204,000 | 3,192,000 | 2,424,400 |
estimated costs to complete as of year-end | 5,396,000 | 2,204,000 | 0 |
billings during the year | 2,140,000 | 3,256,000 | 4,604,000 |
cash collections during the year | 1,870,000 | 3,200,000 | 4,930,000 |
Required:
1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.
2a. | In the journal below, complete the necessary journal entries for the year 2016 (credit "Various accounts" for construction costs incurred).
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started