In 2017, Dreyer Corp. began construction work under a 3-year contract, which represents a single performance obligation. The contract price is $800,000, and the performance
In 2017, Dreyer Corp. began construction work under a 3-year contract, which represents a single performance obligation. The contract price is $800,000, and the performance obligation is satisfied over time. The financial statement presentations relating to this contract on December 31, 2017, follow:
Required:
1. How much cash did Dreyer collect during 2017?
2. What percentage complete is Dreyer as of the end of 2017?
3. What is the estimated gross profit before tax on the contract as of the end of 2017?
Balance Sheet Accounts receivable Construction in progress Less: Progress billings Cost of uncompleted contract in excess of billings $15,000 $ 50,000 (47,000) 3,000 Income Statement Gross profit (before tax) on the contract $10,000
Step by Step Solution
3.49 Rating (162 Votes )
There are 3 Steps involved in it
Step: 1
Answer1 KING CONSTRUCTION COMPANY Gross profitLoss 2017 Particulars Amount ...See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started