Question

1 Approved Answer

In 2018, SM Residences entered into a 3-year agreement in to construct a condominium project for a contract price of P10,000,000. SM recognizes construction contract

In 2018, SM Residences entered into a 3-year agreement in to construct a condominium project for a contract price of P10,000,000. SM recognizes construction contract under the percentage of completion method. For the year ended 2018, the following balances were found in SM's books: Progress Billings P2,000,000; Accounts Receivable P1,000,000; Construction in Progress P3,500,000, Costs incurred to date P2,800,000. For 2019, the balances are Progress Billings P3,000,000; Accounts Receivable P1,200,000; Construction in Progress P6,500,000, Costs incurred to date 5,500,000.

What is the percentage of completion in 2019?

*Please present in a good accounting form. Thank you!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamental Accounting Principles

Authors: John J Wild, Ken Shaw

24th edition

1259916960, 978-1259916960

More Books

Students also viewed these Accounting questions

Question

Discuss diversity and why it is important.

Answered: 1 week ago

Question

2. Value-oriented information and

Answered: 1 week ago

Question

1. Empirical or factual information,

Answered: 1 week ago

Question

1. To take in the necessary information,

Answered: 1 week ago