Question
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:
2018
2019
2020
Cost incurred during the year
$
3,344,000
$
3,960,000
$
1,645,600
Estimated costs to complete as of year-end
5,456,000
1,496,000
0
Billings during the year
2,800,000
4,504,000
2,696,000
Cash collections during the year
2,600,000
4,400,000
3,000,000
Westgate Construction uses the completed contract method of accounting for long-term construction contracts.
Required:
1.Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a.In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
2-b.In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).
2-c.In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $3,344,000 $3,960,000 $1,645,600 Estimated costs to complete as of year-end 5,456,000 1,496,000 Billings during the year 2,800,000 4,504,000 2,696,000 Cash collections during the year 2,600,000 4,400,000 3,000,000 Westgate Construction uses the completed contract method of accounting for long- term construction contracts Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2019 credit "Various accounts" for construction costs incurred) 2-c. In the journal below, complete the necessary journal entries for the year 2020 credit "Various accounts" for construction costs incurred)Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started