Answered step by step
Verified Expert Solution
Link Copied!

Question

...
1 Approved Answer

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,184,000 $ 3,510,000 $ 2,316,600 Estimated costs to complete as of year-end 5,616,000 2,106,000 0 Billings during the year 2,120,000 3,574,000 4,306,000 Cash collections during the year 1,860,000 3,400,000 4,740,000 Westgate recognizes revenue over time according to percentage of completion. rev:

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2018 2019 2020 Cost incurred during the year $ 2,184,000 $ 3,860,000 $ 3,260,000 Estimated costs to complete as of year-end 5,616,000 3,160,000 0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Global Marketing

Authors: Warren J. Keegan, Mark C. Green

9th edition

978-9352865284

Students also viewed these Accounting questions