Question
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:
2018 | 2019 | 2020 | |
Cost incurred during the year | 2,400,000 | 3,600,000 | 2,200,000 |
Estimated costs to complete as of year-end | 5,600,000 | 2,000,000 | 0 |
Billings during the year | 2,000,000 | 4,000,000 | 4,000,000 |
Cash collections during the year | 1,800,000 | 3,600,000 | 4,600,000 |
2-a. In the journal below, complete the necessary journal entries (construction costs, progress billings, cash collections, gross profit/loss) for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries (construction costs, progress billings, cash collections, gross profit/loss) for the year 2019 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries (construction costs, progress billings, cash collections, gross profit/loss) for the year 2020 (credit "Various accounts" for construction costs incurred). | |||||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started