In 2020, ABS Construction Co. was contracted to building Village Company's private road network for $10,000,000. The project was estimated to be completed in two

In 2020, ABS Construction Co. was contracted to building Village Company's private road network for $10,000,000. The project was estimated to be completed in two years and the contract provided for:

a. 5% mobilization fee (to be deducted from the last billing) payable within 15 days after the signing of the contract; 10% retention provision on all billings, and

b. Payment of progress billings within 10 days from acceptance

ABS, which uses the percentage of completion method of accounting, estimated a 25% gross margin on the project. By the end of 2020, ABS has presented progress billings corresponding to 50% completion. All of the progress billings presented in 2020 were accepted except the last one for 10% was accepted on January 5,2021. With the exception of one bill for 8% which was due on January 7,2021, All of the buildings accepted in 2020 were settled. Payments made by Village Company in 2020 amounted to?:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Davis, Charles E., Elizabeth

1st Edition

0471699608, 978-0471699606

More Books

Students also viewed these Accounting questions