Question

1 Approved Answer

In 2020, Sansibon Company began construction work on a contract with a contract price of $8,700,000. Other data are as follows: Required Assuming Sansibon uses

In 2020, Sansibon Company began construction work on a contract with a contract price of $8,700,000. Other data are as follows:

Required

  1. Assuming Sansibon uses the percentage-of-completion method:
    1. How much gross profit should be recognized in 2020?
    2. Show Sansibons journal entries for activity during 2020.
    3. Show Sansibons journal entry to record revenue at the end of 2020.
    4. How much construction expense should be recognized in 2021?
    5. Show Sansibons journal entry to record revenue at the end of 2021.

  1. Assuming Sansibon uses the completed-contract method:
    1. How much construction revenue should be recognized in 2020?
    2. How much construction expense should be recognized in 2021?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

ISE Business Accounting

Authors: Frank Wood, Alan Sangster

8th Edition

0273638408, 9780273638407

More Books

Students also viewed these Accounting questions