Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,600,000. Long recognizes revenue over time according to percentage

In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,600,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows:

Balance Sheet
Accounts receivable (from construction progress billings) $ 40,000
Construction in progress $ 200,000
Less: Billings on construction contract (196,000 )
Cost and profit of uncompleted contracts in excess of billings 4,000

Income Statement
Income (before tax) on the contract recognized in 2021 $ 30,000

Required: 1. What was the cost of construction actually incurred in 2021? 2. How much cash was collected in 2021 on this contract? 3. What was the estimated cost to complete as of the end of 2021? 4. What was the estimated percentage of completion used to calculate revenue in 2021? (Round your percentage answer to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

=+b) What might you consider doing next?

Answered: 1 week ago

Question

1. Let a, b R, a Answered: 1 week ago

Answered: 1 week ago