In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023

Cost incurred during the year: $2,580,000 $3,830,000 $3,230,000

Est. costs- complete for year-end:$ 6,020,000 3,130,000 $0

Billings during the year: 2,060,000 4,562,000 3,378,000

Cash collections during the year: 1,830,000 4,200,000 3,970,000

Westgate recognizes revenue over time according to percentage of completion.

Calculate the amount of revenue and gross profit(loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Equations & Answers

Authors: Barcharts, BarCharts Inc

1st Edition

1423218248, 9781423218241

More Books

Students also viewed these Accounting questions

Question

Discuss what happens when children develop two languages.

Answered: 1 week ago

Question

3. Tactical/strategic information.

Answered: 1 week ago

Question

3. To retrieve information from memory.

Answered: 1 week ago

Question

2. Value-oriented information and

Answered: 1 week ago