In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023

Cost incurred during the year: $2,580,000 $4,042,000 $2,175,800

Est. costs- complete for year-end:$ 6,020,000 1,978,000 $0

Billings during the year: 2,060,000 4,562,000 3,378,000

Cash collections during the year: 1,830,000 4,200,000 3,970,000

Westgate recognizes revenue over time according to percentage of completion.

Calculate the amount of revenue and gross profit(loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Detecting Accounting Fraud Analysis And Ethics

Authors: Cecil Jackson

1st Edition

0133078604, 9780133078602

More Books

Students also viewed these Accounting questions

Question

What is the Conceptual Framework of the FASB?

Answered: 1 week ago

Question

3. How much information do we need to collect?

Answered: 1 week ago

Question

2. What types of information are we collecting?

Answered: 1 week ago

Question

5. How quickly can we manage to collect the information?

Answered: 1 week ago