In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

image text in transcribedimage text in transcribedimage text in transcribed

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,550,000 5,950,000 2,050,000 1,825,000 2022 $4,250,000 1,700,000 4,750,000 4,100,000 2023 $1,870,000 0 3,200,000 4,075,000 Westgate recognizes revenue over time according to percentage of completion. 2023 $ Revenue Gross profit (loss) 2021 3,000,000 $ 450,000 $ 2022 5,000,000 $ 750,000 $ 2,000,000 130,000 $ 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) 2021 2022 Balance Sheet (Partial) Current assets: 0 0 Current liabilities

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: J. David Spiceland, James Sepe, Mark Nelson, Wayne Thomas

10th edition

1260481956, 1260310175, 978-1260481952

More Books

Students also viewed these Accounting questions