Question
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,100,000 | $ | 2,450,000 | $ | 2,695,000 | |||
Estimated costs to complete as of year-end | 4,900,000 | 2,450,000 | 0 | ||||||
Billings during the year | 2,200,000 | 2,350,000 | 5,450,000 | ||||||
Cash collections during the year | 1,900,000 | 2,300,000 | 5,800,000 | ||||||
Westgate recognizes revenue over time according to percentage of completion.
2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).
- Req 2A
- e the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
No | Date | General Journal | Debit | Credit |
---|---|---|---|---|
1 | 2021 | Construction in progress | 2,100,000 | |
Various accounts | 2,100,000 | |||
2 | 2021 | Accounts receivable | 2,200,000 | |
Billings on construction contract | 2,200,000 | |||
3 | 2021 | Cash | 1,900,000 | |
Accounts receivable | 1,900,000 | |||
4 | 2021 | Construction in progress | ||
Cost of construction | ||||
Revenue from long-term contracts |
- Req 2B
In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
No | Date | General Journal | Debit | Credit |
---|---|---|---|---|
1 | 2022 | Construction in progress | 2,450,000 | |
Various accounts | 2,450,000 | |||
2 | 2022 | Accounts receivable | 2,350,000 | |
Billings on construction contract | 2,350,000 | |||
3 | 2022 | Cash | 2,300,000 | |
Accounts receivable | 2,300,000 | |||
4 | 2022 | Construction in progress | ||
Cost of construction | ||||
Revenue from long-term contracts |
In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
req c
No | Date | General Journal | Debit | Credit |
---|---|---|---|---|
1 | 2023 | Construction in progress | 2,695,000 | |
Various accounts | 2,695,000 | |||
2 | 2023 | Accounts receivable | 5,450,000 | |
Billings on construction contract | 5,450,000 | |||
3 | 2023 | Cash | 5,800,000 | |
Accounts receivable | 5,800,000 | |||
4 | 2023 | Construction in progress | ||
Cost of construction | ||||
Revenue from long-term contracts |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started