In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000
Estimated costs to complete as of year-end 4,900,000 2,450,000 0
Billings during the year 2,200,000 2,350,000 5,450,000
Cash collections during the year 1,900,000 2,300,000 5,800,000

Westgate recognizes revenue over time according to percentage of completion.

2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).

  • Req 2A
  • e the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)

No Date General Journal Debit Credit
1 2021 Construction in progress 2,100,000
Various accounts 2,100,000
2 2021 Accounts receivable 2,200,000
Billings on construction contract 2,200,000
3 2021 Cash 1,900,000
Accounts receivable 1,900,000
4 2021 Construction in progress
Cost of construction
Revenue from long-term contracts

  • Req 2B

In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)

No Date General Journal Debit Credit
1 2022 Construction in progress 2,450,000
Various accounts 2,450,000
2 2022 Accounts receivable 2,350,000
Billings on construction contract 2,350,000
3 2022 Cash 2,300,000
Accounts receivable 2,300,000
4 2022 Construction in progress
Cost of construction
Revenue from long-term contracts

In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred). (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)

req c

No Date General Journal Debit Credit
1 2023 Construction in progress 2,695,000
Various accounts 2,695,000
2 2023 Accounts receivable 5,450,000
Billings on construction contract 5,450,000
3 2023 Cash 5,800,000
Accounts receivable 5,800,000
4 2023 Construction in progress
Cost of construction
Revenue from long-term contracts

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Integrated Reporting

Authors: Chiara Mio

1st Edition

1137551488, 9781137551481

More Books

Students also viewed these Accounting questions

Question

Explain how to reward individual and team performance.

Answered: 1 week ago