In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000
Estimated costs to complete as of year-end 5,600,000 2,000,000 0
Billings during the year 2,000,000 4,000,000 4,000,000
Cash collections during the year 1,800,000 3,600,000 4,600,000

Westgate recognizes revenue over time according to percentage of completion.

Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Revenue $3,000,000 ? ?
Gross profit (loss) $600,000 ? ?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Cost Accounting For Health Care Organizations

Authors: Steven Finkler, Judith Baker, David Ward

3rd Edition

0810235447, 9780763738136

More Books

Students also viewed these Accounting questions

Question

8. Name the three catecholamine neurotransmitters.

Answered: 1 week ago