In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400
Estimated costs to complete as of year-end 5,396,000 2,204,000 0
Billings during the year 2,140,000 3,256,000 4,604,000
Cash collections during the year 1,870,000 3,200,000 4,930,000

Westgate recognizes revenue over time according to percentage of completion.

4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Costs incurred during the year $ 2,204,000 $ 3,870,000 $ 3,270,000
Estimated costs to complete as of year-end 5,396,000 3,170,000 0

revenue

gross profit

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Financial Accounting Chapters 1 To 18

Authors: Jerry J. Weygandt, Donald E. Kieso, Paul D. Kimmel

12th Edition

9781118978740

More Books

Students explore these related Accounting questions

Question

Discuss various types of training methods.

Answered: 3 weeks ago