Question

1 Approved Answer

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600
Estimated costs to complete as of year-end 5,810,000 1,826,000 0
Billings during the year 2,030,000 4,444,000 3,526,000
Cash collections during the year 1,815,000 3,900,000 4,285,000

Westgate recognizes revenue over time according to percentage of completion.

2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Building Accounting Systems Using Access 2010

Authors: James Perry, Richard Newmark

8th Edition

1111530998, 978-1111530990

More Books

Students also viewed these Accounting questions