Answered step by step
Verified Expert Solution
Question
1 Approved Answer
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2024 $ 2,100,000 5,400,000 2,150,000 2025 $ 3,150,000 2026 $ 2,475,000 2,250,000 3,100,000 3,100,000 4,750,000 5,025,000 1,875,000 Westgate recognizes revenue over time according to percentage of completion. 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign. Costs incurred during the year Estimated costs to complete as of year-end 2024 $ 2,100,000 5,400,000 2025 $ 3,875,000 4,250,000 2026 $ 4,125,000 0 Answer is complete but not entirely correct. 2024 Revenue $ 2,800,000 $ Gross profit (loss) $ 700,000 $ 2025 3,043,521 (831,479) 2026 $ 4,156,479 (31,479)
Step by Step Solution
★★★★★
3.37 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
Based on the provided information and calculations the correct amounts of rev...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started