In a certain month a company has to schedule the following orders for execution (see table). Execution can start from and including day 0.
In a certain month a company has to schedule the following orders for execution (see table). Execution can start from and including day 0. Order arrival day (of this month) processing time in days to be delivered on day (of this month) A 4 2 12 B 0 12 30 C 1 6 29 D 2 1 14 E 3 10 28 Calculate the average throughput time and average lateness for these 5 orders based on the Longest Operation Time rule. Show how you come to your answers. Activate Windows