In a construction, Concrete Pouring and Mould Removal works are consecutive jobs and it is possible to carry out each job at a different pace.As
In a construction, "Concrete Pouring" and "Mould Removal" works are consecutive jobs and it is possible to carry out each job at a different pace.As the cost changes according to the selected speed, the probabilities of the completion time of the work also change. Contractor's previous experiencehas prepared the following table for costs and possibilities based on
a. Calculate the expected (average) value of the cost in tabular form when work is done at various speeds. at least costWrite down how fast you need to do it.
a. Calculate the expected (average) value of the cost in tabular form when work is done at various speeds. at least costWrite down how fast you need to do it.
b. Suppose that if two jobs cannot be completed in 6 days, the contractor has to pay a penalty of $1000 (US$) per day. Probabilities Since these two events calculated are separate (that is, they cannot occur together), it takes 7 days for two jobs to be completed.Calculate the probabilities and the expected value of the penalty to be paid accordingly, in tabular form.
c.Calculate the expected value of the Total Cost in tabular form, interpret the result and find out what the best solution is.write.
S.3 Bir inaatta "Beton Dkme", "Kalp Skme" ileri birbirini izleyen iler olup her bir ii farkl hizda yrtmek mmkndr. Seilen hza gre maliyet deitii gibi iin tamamlanma sresinin olaslklar da deimektedir. Yklenici daha nceki deneyimlerine dayanarak maliyet ve olaslklar iin aadaki tabloyu hazrlamtr. Hz) 2 Gnde 3 Gnde bitirme bitirme olasl olasl 0,3 0,4 0,5 I (Beton Dkme) I II (Kalp Skme) 11 a. Bl C. B2 KI K2 Gnlk Maliyet($) 120 150 200 250 0,4 0,2 0,5 0,5 4 Gnde bitirme olasl 0,3 0,3 0,2 ilerin eitli hzlarda yapldnda maliyetin beklenen (ortalamas) deerini tablo eklinde hesaplayiniz. En az maliyetle hangi hzla yapmak gerektiini yaznz. b. iki i 6 gnde tamamlanamazsa yklenici gnde 1000$ (ABD Dolan) ceza demesi gerektiini dnelim. Olaslklan hesaplanan bu iki olay ayrk olduu iin (yani ikisi birlikte meydana gelemeyeceine gre) iki i iin 7 gnde bitirilme olaslklar ve buna gre denecek cezann beklenen deerini tablo eklinde hesaplaynz. Toplam Maliyetin beklenen deerini tablo eklinde hesaplaynz, sonucu yorumlayiniz ve en iyi zmn ne olduunu yaznz. 0,1 0,3 tir Temellerden her birinin kme olasl 0,115 dir. Temellerden heranlayanz
Step by Step Solution
★★★★★
3.37 Rating (163 Votes )
There are 3 Steps involved in it
Step: 1
a Speed days 1 2 3 4 5 6 Probability 10 20 30 20 10 10 Cost day 100 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started