In a construction project, the engineer responsible for designing all the structures of a facility is hired by another company and provides one week's notice.
In a construction project, the engineer responsible for designing all the structures of a facility is hired by another company and provides one week's notice. This poses a serious problem for the project as it is one of the critical points and was not included in the risk register. What should be done? Select the correct answer Conduct a new risk identification. Create a temporary solution. Notify the project sponsor. Evaluate the risk identification tools used