In a critical chain implementation, you observed that you completed 75% of the project and consumed 60% of the project buffer. Which of the following
In a critical chain implementation, you observed that you completed 75% of the project and consumed 60% of the project buffer. Which of the following is correct?
- You should pause the project and re-assess the size of the project buffer
- You should shift a portion of the project buffer to the feeding buffer
- You should remove all the resource buffers
- More than one of the above statements is correct
- None of them is correct