In a Finish to Start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity 5 days before its predecessor
In a Finish to Start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity days before its predecessor is complete. This is accomplished by providing days of
Question Answer
a
lag
b
crashing
c
lead
d
fasttracking